Question: Problem 4 : A project utilizing experienced drillers will require drilling and blasting of low - silica dolomite, average efficiency 5 0 - min hour.
Problem :
A project utilizing experienced drillers will require drilling and blasting of lowsilica dolomite, average efficiency min hour. No field drilling tests were conducted. It is proposed to use a in B downhole drill at psi. The drills to be used have a singlepass capability of and take steel in lengths. The blasting pattern will be a grid with of subdrilling. On the average, the specified finish grade is below the existing ground surface. Determine the drilling production, assuming it takes min to change a in downhole hammer. Find the following:
total drill depth ft
drill time min
change steel time min
blow hole time min
move drill time min
align steel time min
change bit time min
total drill time per each hole min
operating rate ftmin
hourly production including production efficeincy fthr
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock