Question: Problem 4: An operation has: Design capacity: 200 units per day Effective capacity: 150 units per day Actual output: 100 units per day What are

 Problem 4: An operation has: Design capacity: 200 units per day

Problem 4: An operation has: Design capacity: 200 units per day Effective capacity: 150 units per day Actual output: 100 units per day What are its a) utilization and b) efficiency? Doblem