Question: Problem 4 : Completely crash the following network schedule using complex compression, and find the optimum time and least cost. Draw the cost vs .

Problem 4:
Completely crash the following network schedule using complex compression, and find the optimum time and least cost. Draw the cost vs. time curve.
\table[[Activity,Duration,Cost, $],[Normal,Crash,Normal,Crash 1,Crash 2,Crash 3,Crash 4],[A,6,4,800,890,1010,,],[B,12,8,1100,1225,1350,1475,],[C,10,6,1400,1475,1560,1650,1760],[D,8,5,1000,1035,1115,1195,1295],[E,6,4,900,965,1040,1130,],[F,4,3,800,825,865,,]]
Overhead Costs =$100/day
 Problem 4: Completely crash the following network schedule using complex compression,