Question: Problem 4 Consider the following projects: Cash Flows Project C0 C1 C2 C3 C4 C5 A -2.500 +2500 0 0 0 0 B -2.000 +1.000
Problem 4
Consider the following projects:
| Cash Flows | ||||||
| Project | C0 | C1 | C2 | C3 | C4 | C5 |
| A | -2.500 | +2500 | 0 | 0 | 0 | 0 |
| B | -2.000 | +1.000 | +1.000 | +4.000 | +1.000 | +2000 |
| C | -3.000 | +1.000 | +1.000 | 0 | +1.000 | +2000 |
1-If the opportunity cost of capital is 10%, what is the NPV of each project?
2-Calculate the payback period for each project ?
3-Which project(s) would a firm using the payback rule accept if the cutoff period were 3 years ?
4-Calculate the discounted payback period for each project ?
5-Which project(s) would a firm using the disounted payback rule accept if the cutoff period were 3 years ?
Problem 5
A $1,000 bond with a 4 years life is paying a semiannual coupon at an annual rate of 6%. The required rate of return is 5%.
1-Compute the PV of the bond
2-Compute the duration of the bond ?
3-Compute and interpret the volatility of the bond (modified duration)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
