Problem 4. Construction Method Selection (25 marks)
You are the production manager for a very large construction company that is about to start a major
concrete pour that is estimated to last for 10 days. Your primary job during this time is to provide the
necessary forms each day:
To meet these requirements, you have three options: 1) you can purchase new forms for $200
each; 2) you can recondition used forms using a standard process that takes 4 days and costs $25 per form;
or 3) you can recondition forms using a special fast process that takes 2 days and costs $75 each. Assume
that the company supplying you with forms has sufficient inventory to supply all new forms if necessary.
Also, you have no forms prior to the start of this operation.
Formulate a linear program that will suggest a strategy for meeting the demand for forms at least
total cost.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!