Question: Problem 4 (designed to be used with the NORMDIST tutorial) For the following problem, please: Draw the network and specify the critical path Find the

Problem 4 (designed to be used with the NORMDIST

Problem 4 (designed to be used with the NORMDIST tutorial) For the following problem, please: Draw the network and specify the critical path Find the expected completion time for the project Find the probability of completing the project in 25 days or less, 20 days or more and between 19 and 22 days. Immed. Pred a m b Activity A 1 5 B A 2 2 1 5 D B 7 9 E 3 4 11 4 6 8 F G B, C D D, E F, G 2 4 6 H 3 5 7