Question: Problem 4 : Fundraising for Academic Agricultural Projects ( 3 0 points total ) A gentleman farmer works wisely on academic projects to raise funds
Problem : Fundraising for Academic Agricultural Projects points total
A gentleman farmer works wisely on academic projects to raise funds for his true passion, farming.
He has identified seven tasks and developed threetime estimates all in days of the next big
project on the farm, replacing the fence at the comedy pasture. Tasks, precedence requirements,
and time estimates including optimistic, most likely, and pessimistic completion times in days, are
shown in the table below. For some, the expected duration and variance have already been
computed.
a points What is the value of the missing item labeled a in the table above? NOTE:
Show your calculation below
b points What is the value of the missing item labeled b in the table above?
c points Draw the network diagram AON for this project. Clearly label earliest start,
earliest finish, latest start, and latest finish for each activity.
d points Specify the critical path.
e points State the project's expected duration.
f points What is the slack of each path? Show methods.
g points What is the standard deviation of the critical path? NOTE: Round to decimals
h points What is the probability that they complete this project between and days?
NOTE: You only need to consider the critical path
i points The project manager wants to know the duration within which he accepts no
more than risk of not finishing the project. NOTE: Only consider the critical path
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock