Question: Problem 4 Refer to the Solved Problem 2 in your textbook, ( or presentation slides ) , and resolve it again using the changed data

Problem 4
Refer to the Solved Problem 2 in your textbook, (or presentation slides), and resolve it again using the changed data below (D is now 70).
A company is setting up an assembly line to produce 192 units per 8-hour shift. The following table identifies the work elements, times, and immediate predecessors:
Work Element
Time (sec)
Immediate Predecessor(s)
A
40
None
B
80
A
C
30
D, E, F
D
70
B
E
20
B
F
15
B
G
120
A
H
145
G
I
130
H
J
115
C, I
Total 765
a.What is the desired cycle time (in seconds)?
b.What is the theoretical minimum number of stations?
c.Use the longest task time approach to allocate tasks to workstations and show your solution on the table below.
d.What is the efficiency and balance delay of the solution found?
e.If the company wants to produce more units, which workstation do you think will be limiting it from future production increases (bottleneck)?(look at the idle time of each workstation)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!