Question: Problem 4. Solving for D for a given probability (6 points) Time (Weeks) A M 1 Immediate Activity Predecessor A B 4 8 7 8

Problem 4. Solving for D for a given probability

Problem 4. Solving for D for a given probability (6 points) Time (Weeks) A M 1 Immediate Activity Predecessor A B 4 8 7 8 5 b 10 8 6 T: G2 7 1 8 0 50.1111 0 4 There is an 80 percent chance the project can be completed in D weeks or less. What is the value of D? Answer Record answer with two digits after the decimal point