Question: Problem (4): Use the information below to compute the probability of completing the project before 70 days. Activity Pred. a (opt) b (pes) 10
Problem (4): Use the information below to compute the probability of completing the project before 70 days. Activity Pred. a (opt) b (pes) 10 8 8 28 24 13 28 14 17 8 45 A BCDEFGH - Y J K None None A, B CEC C D, F, G G, F H I, J INNGANG 4 2 2 16 6 1 4 2 5 2 17 m 7 4 5 19 9 7 10 5 8 5 29 te N 7 4 5 20 11 7 12 6 9 5 30 Variance 1 LLADAGATIN 1 1 4 9 4 16 4 4 1 22
Step by Step Solution
3.45 Rating (158 Votes )
There are 3 Steps involved in it
To compute the probability of completing the project before 70 days using the given information we c... View full answer
Get step-by-step solutions from verified subject matter experts
