Question: Problem # 4 You are given below a table showing activities, their required sequence, and time requirements for the new introduction project. 5 Required: a.

Problem \# 4 You are given below a table showing activities, their required sequence, and time requirements for the new introduction project. 5 Required: a. Draw an AOA diagram. b. Convert the AOA diagram into an AON diagram. c. Identify different paths in the network showing critical path. d. Find out slacks of each path. e. How many weeks will it take to complete the marketing operation? Problem \# 4 You are given below a table showing activities, their required sequence, and time requirements for the new introduction project. 5 Required: a. Draw an AOA diagram. b. Convert the AOA diagram into an AON diagram. c. Identify different paths in the network showing critical path. d. Find out slacks of each path. e. How many weeks will it take to complete the marketing operation