Question: Problem 4-9 (Static) The R&D department is planning to bid on a large project for the development of a new communication system for commercial planes.
Problem 4-9 (Static)
The R&D department is planning to bid on a large project for the development of a new communication system for commercial planes. The accompanying table shows the activities, times, and sequences required:
| ACTIVITY | IMMEDIATE PREDECESSOR | TIME (WEEKS) |
| A | 3 | |
| B | A | 2 |
| C | A | 4 |
| D | A | 4 |
| E | B | 6 |
| F | C, D | 6 |
| G | D, F | 2 |
| H | D | 3 |
| I | E, G, H | 3 |
b. What is the critical path? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.)
check all that apply 1
- A-C-F-G-I
- A-B-E-I
- A-D-H-I
- A-D-F-G-I
c. Suppose you want to shorten the completion time as much as possible, and you have the option of shortening any or all of B, C, D, and G each one week. Which would you shorten? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.)
check all that apply 2
- B
- C
- D
- G
d-1. What is the new critical path? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box for a wrong answer.)
check all that apply 3
- A-C-F-G-I
- A-D-H-I
- A-B-E-I
- A-D-F-G-I
d-2.What is the earliest completion time for the new critical path?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
