Question: Problem 5 - 1 8 ( Static ) The following CPM network has estimates of the normal time in weeks listed for the activities: A

Problem 5-18(Static)
The following CPM network has estimates of the normal time in weeks listed for the activities:
A diagram shows critical path through A, B, C, D, E, F, and G.A diagram shows a critical path through A, B, C, D, E, F and G. It shows circles labeled as A (7), B (2), C (4), D (5), E (2), F (4) and G (5). A is connected to B and C. B and C are connected to D. D is connected to E and F and they lead to G.
a. Identify the critical path.
multiple choice 1
A-B-D-E-G
A-C-D-E-G
A-B-D-F-G
A-C-D-F-G
b. What is the length of time to complete the project?
c. Which activities have slack, and how much?
multiple choice 2
C,2 weeks; F,3 weeks.
C,1 week; E,2 weeks.
D,1 week; E,2 weeks.
B,2 weeks; E,2 weeks.
Here is a table of normal and crash times and costs.
ACTIVITY NORMAL TIME CRASH TIME NORMAL COST CRASH COST
A 76 $7,000 $8,000
B 215,0007,000
C 439,00010,200
D 543,0004,500
E 212,0003,000
F 424,0007,000
G 545,0008,000
d-1. Which activities would you shorten to cut two weeks from the schedule in a rational fashion?
multiple choice 3
B, D
A, E
B, C
A, C
d-2. What would be the total incremental cost?
d-3. Is the critical path changed?
multiple choice 4
Yes

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!