Question: Problem 5 - 5 ( Algo ) Wild Widget must set up an assembly line for widgets. Forecasts show that 4 2 units per hour
Problem Algo
Wild Widget must set up an assembly line for widgets. Forecasts show that units per hour should be produced. The tasks required, task times, and precedence relationships are as follows:
tableTaskTime secondsPredecessorsABACADC BEDFDGE F
pictureClick here for the Excel Data File
a What is the takt time?
b What is the theoretical number of workstations?
c Assign the tasks to the workstations to balance the line using the longest operating time rule.
d What is the efficiency of the balanced line?
e If demand decreased to units per hour, what would be the new takt time?