Question: Problem 5 - 6 ( Algo ) A project to build a new bridge seems to be going very well since the project is well
Problem Algo
A project to build a new bridge seems to be going very well since the project is well ahead of schedule and costs seem to running very low. A major milestone has been reached where the first two activities have been totally completed and the activity is percent complete. The planners were expecting to be only percent through the third activity at this time. first activity involves prepping the site for the bridge. It was expected that this would cost $ and it was done for $ The second activity was the pouring of concrete for the bridge. This was expected to cost $ but actually done for $ The third and final activity is the actual construction of the bridge superstructure. This was expected to cost a total of $ To date, they have spent $ on the superstructure.
Calculate the schedule variance, schedule performance index, and cost performance index for the project to date.
Note: Round your "performince index" values to decimal places.
Answer is complete but not entirely correct.
tableSchedule variance,$
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock