Question: Problem 5 - 6 ( Algo ) Golf Carts Incorporated must set up an assembly line for golf carts. Forecasts show that 8 units per
Problem Algo
Golf Carts Incorporated must set up an assembly line for golf carts. Forecasts show that units per day should be produced. The plant
operates one hour shift each day and runs the line continuously during the shift. The tasks required, task times, and precedence
relationships are as follows:
Click here for the Excel Data File
a What is the takt time?
b What is the theoretical number of workstations?
c Assign the tasks to the workstations to balance the line using the longest operating time rule.
d What is the efficiency of the balanced line?
e If demand increased to units per day, what would be the new takt time?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock