Question: Problem 5 - 7 ( Algo ) The following activities are part of a project to be scheduled using CPM: table [ [ ACTIVITY

Problem 5-7(Algo)
The following activities are part of a project to be scheduled using CPM:
\table[[ACTIVITY,IMMEDRATE PREDECESSOR,TIME,(WEEKS)],[A,and,,8],[B,A :',,5],[C,A,,9],[D,C,,6],[E,B%media:cm.png%,,4],[F,8),,],[G,E%media:cm.png%,,4]]
a. What is the critical path?
A-C-D-F-G
A-B-E-G
A-B-D-F-G
A-C-D-E-G
b. How many weeks will it take to complete the project?
c. How much slack does activity B have?
Slack of activity B 26 weeks
 Problem 5-7(Algo) The following activities are part of a project to

Step by Step Solution

There are 3 Steps involved in it