Question: Problem 5 - 8 ( Static ) Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 1 B A 4
Problem Static
Schedule the following activities using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME WEEKS
A
B A
C A
D B
E C D
F D
G F
H E G
What is the critical path?
multiple choice
ABDEH
ACEH
ACDFG
ABDFGH
How many weeks will it take to complete the project?
Which activities have slack, and how much?
multiple choice
B weeks; D week; and E week.
C weeks; F week; and G week.
D weeks; G week; and H week.