Question: Problem 5 - 8 ( Static ) Schedule the following activities using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME ( WEEKS ) A 1 B A 4

Problem 5-8(Static)
Schedule the following activities using CPM:
ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS)
A 1
B A 4
C A 3
D B 2
E C, D 5
F D 2
G F 2
H E, G 3
What is the critical path?
multiple choice 1
A-B-D-E-H
A-C-E-H
A-C-D-F-G
A-B-D-F-G-H
How many weeks will it take to complete the project?
Which activities have slack, and how much?
multiple choice 2
B,3 weeks; D,1 week; and E,1 week.
C,3 weeks; F,1 week; and G,1 week.
D,2 weeks; G,1 week; and H,1 week.