Question: Problem 5. Please answer to the questions using following table: Activity A B C D E F Immediate Predecessors -- A A A B,C D


Problem 5. Please answer to the questions using following table: Activity A B C D E F Immediate Predecessors -- A A A B,C D Expected Time (Weeks) 5 4 8 7 9 6 Part a: Draw the network diagram for above project using AOA and AON Part b: find the critical path and critical activities for the following project