Question: Problem 5: Please answer True or False for each statement below. Please JUSTIFY your answers with short comments. (Quantitative Project Management) defined in CMMI covers
Problem 5:
Please answer True or False for each statement below. Please JUSTIFY your answers with short comments.
(Quantitative Project Management) defined in CMMI covers project level activities, not the organizational level activities.
An XmR chart is the only method one can use to implement Process Performance Baselines defined in SP 1.4 in the process area OPP (Organizational Process Performance).
Measurement and Analysis (MA) defined in CMMI is placed as a Level 2 PA (Process Area) because it could be used to support activities defined in PAs in Level 3, Level 4, and Level 5.
Model maturity can be obtained without cultural maturity but the opposite is not true.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
