Question: Problem 5. There are six trailers waiting at docking station to be unloaded. The times required to unload each trailer and the times that materials

Problem 5. There are six trailers waiting at

Problem 5. There are six trailers waiting at docking station to be unloaded. The times required to unload each trailer and the times that materials they contain are due in the manufacturing are given in the table: Trailer Promised Time (hours) Unloading Time (hours) A 10 6 B 5 4 35 15 D 25 18 E 20 10 F F 15 12 MUO ||| m a. Sequence the trailers to minimize the number of tardy containers using Moore algorithm. b. Provide the optimal sequence including the six trailers