Question: Problem 5. Use a Gantt Chart and a Network Diagram for the following software project. Activities Duration (days) Connections: A 5 A to B Start
Problem 5. Use a Gantt Chart and a Network Diagram for the following software project. Activities Duration (days) Connections: A 5 A to B Start to Start with a lag of 5 B 4 (A and B) to C Finish to Start C 7 (A and B) to D Finish to Start D 6 (C and D) to E Finish to Start E 9 E to F Finish to Start with a lag of 2 F 10 F to G Finish to Start G 6 F to H Start to Start with a lag of 3 H 26 (G and H) to I Finish to Start I 4