Question: Problem 5-10 The following represents a project that should be scheduled using CPM: IMMEDIATE TIMES (DAYS) ACTIVITY PREDECESSORS a m b 1 4 7 B

Problem 5-10 The following represents a project
Problem 5-10 The following represents a project that should be scheduled using CPM: IMMEDIATE TIMES (DAYS) ACTIVITY PREDECESSORS a m b 1 4 7 B 3 10 A 2 5 8 A 4 6 11 B 1 2 3 F C D 3 5 7 G DE 1 2 6 H F G 2 5 6 b. What is the critical path? BEG-H A-D-F-H A-CF-H A-D-G-H c. What is the expected project completion time? (Round your answer to 3 decimal places.) Project completion time days d. What is the probability of completing this project within 22 days? (Do not round intermediate calculations. Round your a Probability