Question: Problem 6 - 1 0 ( Algo ) Long - term contract; revenue recognition over time [ LO 6 - 8 , 6 - 9

Problem 6-10(Algo) Long-term contract; revenue recognition over time [LO6-8,6-9]
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for
$10,000,000. The road was completed in 2026. Information related to the contract is as follows:
Westgate recognizes revenue over time according to percentage of completion.
Problem 6-10(Algo) Part 2
2-a. In the journal below, complete the necessary journal entries for the year 2024(credit "Cash, Materials, etc." for construction costs
ncurred).
2-b. In the journal below, complete the necessary journal entries for the year 2025(credit "Cash, Materials, etc." for construction costs
ncurred).
2-c. In the journal below, complete the necessary journal entries for the year 2026(credit "Cash, Materials, etc." for construction costs
ncurred). Cash collections during the year
\(1,900,000\)
2,300,000
5,800,000
Westgate recognizes revenue over time according to percentage of completion.
Problem 6-10(Algo) Part 3
3. Complete the information required below to prepare a partial balance sheet for 2024 and 2025 showing any items related to the contract.
Note: Do not round intermediate calculations.
\begin{tabular}{|l|l|l|l|l|}
\hline \multicolumn{1}{|c|}{ Balance Sheet (Partial)} & \multicolumn{2}{c|}{2024} & \multicolumn{2}{|c|}{2025}\\
\hline Current assets: & & & & \\
\hline & & & & \\
\hline & & & & \\
\hline & & & & \\
\hline Current liabilities: & & & & \\
\hline & & & & \\
\hline & & & & \\
\hline & & & & \\
\hline
\end{tabular} Problem 6-10(Algo) Long-term contract; revenue recognition over time [LO6-8,6-9]
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for \(\$ 10,000,000\). The road was completed in 2026. Information related to the contract is as follows:
Westgate recognizes revenue over time according to percentage of completion.
roblem 6-10(Algo) Part 4
. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs curred and costs to complete information.
lote: Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts hould be indicated with a minus sign. Required information
Problem 6-10(Algo) Long-term contract; revenue recognition over time [LO6-8,6-9]
[The following information applies to the questions displayed below.]
In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for \(\$ 10,000,000\). The road was completed in 2026. Information related to the contract is as follows:
Westgate recognizes revenue over time according to percentage of completion.
Problem 6-10(Algo) Part 5
5. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years, assuming the following costs incurred and costs to complete information.
Note: Do not round intermediate calculations and round your final answers to the nearest whole dollar amount. Loss amounts should be indicated with a minus sign.
Problem 6 - 1 0 ( Algo ) Long - term contract;

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!