An assembly line is to be designed to operate 8.5 hours per day and supply a steady demand of 450 units per day. Here are the tasks and their performance times:
TASK PRECEDING TASKS PERFORMANCE TIME (SECONDS) TASK PRECEDING TASKS PERFORMANCE TIME (SECONDS)
a 38 g d 28
b 18 h e 10
c 28 i f 43
d a 23 j g 8
e b 21 k h,i 48
f c 13 l j,k 8
b. What is the workstation cycle time required to produce 450 units per day?