Question: Problem 6 - 1 8 ( Algo ) An assembly line is to be designed to operate 1 3 hours per day and supply a

Problem 6-18(Algo)
An assembly line is to be designed to operate 13 hours per day and supply a steady demand of 325 units per day. Here are the tasks and their performance times:
TASKPRECEDING TASKSPERFORMANCE TIME (SECONDS)TASKPRECEDING TASKSPERFORMANCE TIME (SECONDS)a50gd45b60he40c75if25da65jg35eb90kh,i55fc25lj,k69
b. What is the workstation cycle time required to produce 325 units per day?
c. What is the theoretical minimum number of workstations?
Note: Round upyour answer to the next whole number.
d. Assign tasks to workstations using the longest operating time.
Note: Leave no cells blank - be certain to enter "0" wherever required.
e. What is the efficiency of your line balance, assuming it is running at the cycle time from part (b)?
Note: Round your answer to 1 decimal place.
f. Suppose demand increases by 10 percent. How would you react to this? Assume you can operate only 13 hours per day.
Note: Round your answers to the nearest whole number.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!