Question: Problem 6 - 1 9 ( Algo ) The following tasks are to be performed on an assembly line: TASK SECONDS TASKS THAT MUST PRECEDE
Problem Algo
The following tasks are to be performed on an assembly line:
TASK SECONDS TASKS THAT MUST PRECEDE
A
B A
C B
D B
E C
F D
G E F
H G
The workday is hours long. The demand for completed product is per day.
Find the cycle time required to meet the desired output rate.
Note: Round your answer to decimal place.
What is the theoretical number of workstations required to meet the desired output rate?
Note: Round up your answer to the next whole number.
Balance the line using sequential restrictions and the longestoperatingtime rule. Determine the task under each workstation and the idle time for each such task.
Note: Leave no cells blank be certain to enter wherever required. Round your answers to decimal place.
What is the efficiency of the line balanced as in part d assuming it is running at the cycle time determined in part a
Note: Round your answer to decimal place.
Suppose that demand rose from to units per day. Determine the cycle time. Use the solution obtained in part d
Note: Round your answer for cycle time down to the nearest whole number.
Suppose that demand rose from to units per day. Determine the cycle time. Use the solution obtained in part d
Note: Round your answer for cycle time down to the nearest whole number.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock