Question: Problem 6 (120 Points, Plus 50 Bonus Points) A project manager has compiled a list of major activities that will be required to install a
| Problem 6 (120 Points, Plus 50 Bonus Points) | |||||||||||||||||
| A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships. | |||||||||||||||||
| Activity | Immediate | Estimated Times | |||||||||||||||
| Predecessor | (weeks) | ||||||||||||||||
| A | 2-4-6 | ||||||||||||||||
| D | A | 6-9-10 | |||||||||||||||
| E | D | 7-9-12 | |||||||||||||||
| H | E | 2-3-5 | |||||||||||||||
| F | A | 3-4-8 | |||||||||||||||
| G | F | 5-7-9 | |||||||||||||||
| B | 2-3-4 | ||||||||||||||||
| I | B | 2-3-6 | |||||||||||||||
| J | I | 3-4-5 | |||||||||||||||
| K | J | 4-7-8 | |||||||||||||||
| C | 5-8-11 | ||||||||||||||||
| M | C | 2-2-2 | |||||||||||||||
| N | M | 6-7-11 | |||||||||||||||
| O | N | 8-9-12 | |||||||||||||||
| End | H, G, K, O | ||||||||||||||||
| Note: Estimated times in Column C, "*-*-*", represent the Optimistic, Mostly Likely, and Pessimistic, respectively. | |||||||||||||||||
| Use the Most Likely time estimate for each activity, answer questions a, b, and c. | |||||||||||||||||
| a. What are the activities on its Critical Path? (30 Points) | |||||||||||||||||
| b: What is the expected duration of the project? (30 Points) | |||||||||||||||||
| c: What is the Earliest Start Time for Activity M ? (30 Points) | |||||||||||||||||
| d: What is the Lastest Finish Time for Activity J? (30 Points) |