Question: Problem 6 (120 Points, Plus 50 Bonus Points) A project manager has compiled a list of major activities that will be required to install a

Problem 6 (120 Points, Plus 50 Bonus Points)

A project manager has compiled a list of major activities that will be required to install a computer information system in her firm. The list includes estimated completion times for activities and precedence relationships.

Activity

Immediate Estimated Times
Predecessor (weeks)
A 2-4-6
D A 6-9-10
E D 7-9-12
H E 2-3-5
F A 3-4-8
G F 5-7-9
B 2-3-4
I B 2-3-6
J I 3-4-5
K J 4-7-8
C 5-8-11
M C 2-2-2
N M 6-7-11
O N 8-9-12
End H, G, K, O

Note: Estimated times in Column C, "*-*-*", represent the Optimistic, Mostly Likely, and Pessimistic, respectively.

Use the Most Likely time estimate for each activity, answer questions a, b, and c.

a. What are the activities on its Critical Path? (30 Points)

b: What is the expected duration of the project? (30 Points)

c: What is the Earliest Start Time for Activity M ? (30 Points)

d: What is the Lastest Finish Time for Activity J? (30 Points)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!