Question: Problem 6 :3 Question Help Complete the following MRP record. All gross requirements, beginning inventory levels, and scheduled receipts are shown. E: Click the icon

Problem 6 :3 Question Help Complete the following

Problem 6 :3 Question Help Complete the following MRP record. All gross requirements, beginning inventory levels, and scheduled receipts are shown. E: Click the icon to view the MRP record. Complete the material requirements plan (enter your responses as whole numbers). 1 2 3 4 6 Week ***A2*** LT(weeks) = 1 5 450 150 100 450 400 400 260 Gross requirements Scheduled receipts Projected ending inventory: 150 Net requirements Min. order = 1 Planned receipts