Question: Problem 6. Complete the PERT analysis for the following project. Calculate the expected times and variances for the activities (round to nearest integer). Create the
| Problem 6. | |||||||||||
| Complete the PERT analysis for the following project. Calculate the expected times and variances for the activities (round to nearest integer). | |||||||||||
| Create the Gantt chart using Project and identify the critical activties. | |||||||||||
| What is the probability of completing this project in 42 time-units? Use the Z-table available in your lecture slides. | |||||||||||
| Activity | Predecessor | Optimistic time | Most likely time | Pessimistic time | Expected time | Variance | |||||
| A | - | 1 | 2 | 6 | |||||||
| B | - | 3 | 5 | 7 | |||||||
| C | A | 4 | 8 | 10 | |||||||
| D | B | 3 | 6 | 9 | |||||||
| E | C, D | 5 | 10 | 15 | |||||||
| F | E | 4 | 8 | 12 | |||||||
| G | E | 5 | 7 | 10 | |||||||
| H | G | 6 | 7 | 8 | |||||||
| I | F, H | 9 | 12 | 15 |
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock