Question: Problem 6 : For the project depicted in the activity - on - arrow diagram below ( time units are days ) : a )
Problem :
For the project depicted in the activityonarrow diagram below time units are days:
a What is the critical path?
b How long will it take to complete the project?
c What is the late start time for task B
d What is the slack for task B
e What is the early start time for task C
f What is the slack for task C
g What is the late finish time for task G
h What is the slack for task G