Question: Problem 6 : For the project depicted in the activity - on - arrow diagram below ( time units are days ) : a )

Problem 6:
For the project depicted in the activity-on-arrow diagram below (time units are days):
a) What is the critical path?
b) How long will it take to complete the project?
c) What is the late start time for task B?
d) What is the slack for task B?
e) What is the early start time for task C?
f) What is the slack for task C?
g) What is the late finish time for task G?
h) What is the slack for task G?