Question: Problem 6 . In a learning curve application, 6 5 8 . 5 work hours are required for the third production unit and 6 1

Problem 6. In a learning curve application, 658.5 work hours are required for the third production unit and 615.7 work hours are required for the fourth production unit. Determine
(A) the value of (n) and
(B) the value of (s) which is the slope of the learning curve in Equation (3-5) which is
Zu=K(un)
 Problem 6. In a learning curve application, 658.5 work hours are