Question: Problem. ( 60pts) A project is defined by the list of activities as shown below. a) Draw the AON network for the project, and show
Problem. ( 60pts) A project is defined by the list of activities as shown below. a) Draw the AON network for the project, and show all times. b) What are the critical activities? Why are they critical? c) What is the project duration? d) Now suppose that activity durations of C, F, E, I are subject to uncertainty with the following time estimates available. 1). What is now the project duration? Explain the reasons. ii) What is now the critical path? Why? iii) What is the probability that the project will be completed in less than 47 days iv) What is the completion time corresponding to 6756 probability. Hint. Rounding off should be 2 decimal places. b) arivecel actruties ac stact ACF End