Question: Problem 6-3 A manager wants to assign tasks to workstations as efficiently as possible, and achieve an hourly output of 4 units. The department uses
Problem 6-3
| A manager wants to assign tasks to workstations as efficiently as possible, and achieve an hourly output of 4 units. The department uses a working time of 56 minutes per hour. Assign the tasks shown in the accompanying precedence diagram (times are in minutes) to workstations using the following rules: |
| a. | In order of most following tasks. Tiebreaker: greatest positional weight. |
| Work Station | Tasks |
| I | (Click to select) A, G I D, B, C E, H F, A, G |
| II | (Click to select) E, H I D, B, C D F, A, G |
| III | (Click to select) F, A, G D, B, C I E, H H |
| IV | (Click to select) E, H F, A, G H B,E I |
| b. | In order of greatest positional weight. |
| Work Station | Tasks |
| I | (Click to select) C, D F, D D, C F, G G, H |
| II | (Click to select) F, A, G G, A, B G, H B, C E, H |
| III | (Click to select) D, C, F B,E F, G C, E A |
| IV | (Click to select) A H, I B,E H G |
| c. | What is the efficiency? (Round your answer to 2 decimal places. Omit the "%" sign in your response. ) |
| Efficiency | % |