Question: Problem 6-8 (Algo) Lambda Computer Products competed for and won a contract to produce two prototype units of a new type of computer that
Problem 6-8 (Algo) Lambda Computer Products competed for and won a contract to produce two prototype units of a new type of computer that is based on laser optics rather than on electronic binary bits. The first unit produced by Lambda took 5,000 hours to produce and required $250,000 worth of material, equipment usage, and supplies. The second unit took 4,250 hours and used $237,500 worth of materials, equipment usage, and supplies. Labor is $25 per hour. Use Exhibit 6.5. a. Lambda was asked to present a bid for 10 additional units as soon as the second unit was completed. Production would start immediately. What would this bid be?