Question: Problem 7 - 2 ( Algo ) A job was timed for 6 0 cycles and had an average of 1 . 2 1 minutes

Problem 7-2(Algo)
A job was timed for 60 cycles and had an average of 1.21 minutes per piece. The performance rating was 91 percent, and workday allowances are 5 percent. Determine each of the following:
a. Observed time. (Round your answer to 2 decimal places.)
minutes
b. Normal time. (Round your answer to 2 decimal places.)
Normal time
minutes
c. Standard time. (Round your answer to 2 decimal places.)
Standard time
minutes
 Problem 7-2(Algo) A job was timed for 60 cycles and had

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!