Question: Problem 7 ( Adapted from Winston, 2 0 0 4 ) . Bob is currently building three homes, and he needs to schedule five contractors
Problem Adapted from Winston, Bob is currently building three homes, and he needs to
schedule five contractors to complete tasks at each of the homes. The number of days required for each
contractor to complete the work at each home is given in the following table:
In creating the schedule, Bob wishes to ensure the following:
For each home, excavation is performed first, followed by foundation, framing, plumbing, and
roofing in order
There is only one contractor of each type excavation foundation, framing, plumbing, and
roofing Each contractor can work on only one home at a time. A contractor's work on one
home must be completed before it can begin working on another home.
Part a: Formulate an integerlinear program to determine a schedule that minimizes the number of days
until the last home is completed.
Part b: Solve the problem using AMPLCPLEX and report the obtained optimal solution.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock