Question: Problem 8 - 1 2 ( Algo ) A firm uses a serlal assembly system and needs answers to the following: a . An output
Problem Algo
A firm uses a serlal assembly system and needs answers to the following:
a An output of units per shift hours is desired for a new processing system. The system requires product to pass through
four stations where the work content at each station is seconds. What is the required cycle time for such a system?
Note: Round your answer to the nearest whole number.
Cycle time
seconds
b How efficlent is your system with the cycle time you calculated?
Note: Round your answer to decimal place.
Efficiency
c Station changes and now requires seconds to complete. What will need to be done to meet demand assume only hours
are avallable What is the efficlency of the new system?
Note: Round your answer to decimal place.
To satisfy the demand, station will
and the efficiency is
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock