Question: Problem 8 - 6 ( Algo ) The desired dally output for an assembly line is 4 2 0 units. This assembly line will operate

Problem 8-6(Algo)
The desired dally output for an assembly line is 420 units. This assembly line will operate 595 minutes per day. The following table
contains information on this product's task times and precedence relationships:
b. What is the workstation cycle time?
c. Balance this line using the largest number of following tasks. Use the longest task time as a secondary criterion. (Leave no cells
blank - be certain to enter "0" wherever required.)
d. What is the efficlency of your line balance? (Round your answer to 1 decimal place.)
 Problem 8-6(Algo) The desired dally output for an assembly line is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!