Question: Problem 8 - 9 ( Algo ) An assembly line is to be designed to operate 5 hours per day and supply a steady demand

Problem 8-9(Algo)
An assembly line is to be designed to operate 5 hours per day and supply a steady demand of 300 units per day. Here are the tasks and their performance times:
\table[[TASK,\table[[PRECEDING],[TASKS]],\table[[PERFORMANCE],[TIME],[(SECONDS)]],TASK,\table[[PRECEDING],[TASKS]],\table[[PERFORMANCE TIME],[(SECONDS)]]],[a,-,38,g,d,8],[b,-,33,h,e,10],[c,-,28,i,f,16],[d,a,8,j,g,13],[e,b,18,k,h,i,18],[f,c,38,l,j,k,23]]
b. What is the workstation cycle time required to produce 300 units per day?
Workstation cycle time
seconds per unit
c. What is the theoretical minimum number of workstations?
Note: Round up your answer to the next whole number.
Minimum number of workstations
d. Assign tasks to workstations using the longest operating time.
Note: Leave no cells blank - be certain to enter "0" wherever required.
\table[[Work Station,Task,Idle Time],[I,,],[II,,],[III,,],[IV,,],[V,,]]
 Problem 8-9(Algo) An assembly line is to be designed to operate

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!