Question: Problem 9 - 1 0 ( Algo ) In the following MRP planning schedule for Item J , indicate the correct net requirements, planned -

Problem 9-10(Algo)
In the following MRP planning schedule for Item J, indicate the correct net requirements, planned-order receipts, and planned-orde releases to meet the gross requirements. Lead time is one week.
Note: Leave the cells blank, whenever zero (0) is required.
\table[[ITEM J,WEEK NUMBER],[0,1,2,3,4,5],[Gross requirements,,,73,,47,71],[On-hand,34,,,,,],[Net requirements,,,,,,],[Planned-order receipt,,,,,,],[Planned-order release,,,,,,]]
\table[[,Period,1,2,3,4,5],[\table[[Item: J],[OH: 34],[LT: 1],[SS: 0],[Q: L4L]],Gross requirements,,73,,47,71],[Scheduled receipts,,,,,],[Projected available balance,,,,,],[Net requirements,,,,,],[Planned order receipts,,,,,],[Planned order releases,,,,,]
 Problem 9-10(Algo) In the following MRP planning schedule for Item J,

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!