Question: Problem 9 - 1 1 ( Algo ) Assume that Product Z is made of two units of A and three units of B .

Problem 9-11(Algo)
Assume that Product Z is made of two units of A and three units of B.A is made of four units of C and four of D.D is made of two units of E.
Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks.
Fifty-one units of Product Z are required in Period 10.(Assume that there is currently no inventory on-hand of any of these items.)
b. Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates.
Note: Leave the cells blank, whenever zero (0) is required.
Answer is not complete.
\table[[,Period:,1,2,3,4,5,6,7,8,9,10],[\table[[Item: Z],[OH: 0],[LT: 2],[SS: 0],[Q: L4L]],Gross requirements,,,,,,,,,,62In the following MRP planning schedule for Item J, indicate the correct net requirements, planned-order receipts, and planned-order releases to meet the gross requirements. Lead time is one week.
Note: Leave the cells blank, whenever zero (0) is required.
ITEM J WEEK NUMBER
012345
Gross requirements 775275
On-hand 47
Net requirements
Planned-order receipt
Planned-order release
 Problem 9-11(Algo) Assume that Product Z is made of two units

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!