Question: Problem 9 - 1 8 ( Algo ) Product A is an end item and is made from two units of B and three of

Problem 9-18(Algo)
Product A is an end item and is made from two units of B and three of C.B is made of three units of D and four of E.C is made of three units of F and four of E.
A has a lead time of one week. B, C, and E have lead times of two weeks, and D and F have lead times of three weeks.
b. If 80 units of A are required in Week 10, develop the MRP planning schedule, specifying when items are to be ordered and received.
There are currently no units of inventory on hand.
Note: Leave the cells blank, whenever zero (0) is required.
\table[[,Period:,1,2,3,4,5,6,7,8,9,10],[\table[[Item: A],[OH: 0],[LT: 1],[SS: 0],[Q: L4L]],Gross requirements,,,,,,,,,,],[Scheduled receipts,,,,,,,,,,],[Projected available balance,,,,,,,,,,],[Net requirements,,,,,,,,,,],[Planned order receipts,,,,,,,,,,],[Planned order releases,,,,,,,,,,],[\table[[Item: B],[OH: 0],[LT: 2],[SS: 0],[Q: L4L]],Gross requirements,,,,,,,,,,],[Scheduled receipts,,,,,,,,,,],[Projected available balance,,,,,,,,,,],[Net requirements,,,,,,,,,,],[Planned order receipts,,,,,,,,,,],[Planned order releases,,,,,,,,,,],[Gross renuirements,,,,,,,,,17,]]
 Problem 9-18(Algo) Product A is an end item and is made

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock