Question: Problem 9 - 2 4 ( Algorithmic ) Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the

Problem 9-24(Algorithmic)
Office Automation, Inc., developed a proposal for introducing a new computerized office system that will standardize the electronic archiving of invoices for a particular company. Contained in the proposal is a list of activities that must be accomplished to complete the new office system project. Use the following relevant information about the activities:
Immediate Time (weeks) Cost ($1000s)
Activity Description Predecessor(s) Normal Crash Normal Crash
A Plan needs 983050
B Order equipment A 86120150
C Install equipment B 107100160
D Set up training lab A 764050
E Conduct training course D 1085075
F Test system C, E 3360
Which project network is correct?
(i)(ii)
(iii)(iv)
Develop an activity schedule. If your answer is zero, enter 0.
Earliest Latest Earliest Latest Critical
Activity Start Start Finish Finish Slack Activity
A fill in the blank 2
fill in the blank 3
fill in the blank 4
fill in the blank 5
fill in the blank 6
B fill in the blank 8
fill in the blank 9
fill in the blank 10
fill in the blank 11
fill in the blank 12
C fill in the blank 14
fill in the blank 15
fill in the blank 16
fill in the blank 17
fill in the blank 18
D fill in the blank 20
fill in the blank 21
fill in the blank 22
fill in the blank 23
fill in the blank 24
E fill in the blank 26
fill in the blank 27
fill in the blank 28
fill in the blank 29
fill in the blank 30
F fill in the blank 32
fill in the blank 33
fill in the blank 34
fill in the blank 35
fill in the blank 36
What are the critical activities, and what is the expected project completion time?
Critical Path:
Expected project completion time = fill in the blank 39
weeks.
Assume that the company wants to complete the project in six months or 26 weeks. What crashing decisions do you recommend to meet the desired completion time at the least possible cost? Work through the network and attempt to make the crashing decisions by inspection.
Crash Activities Number of Weeks Cost ($1000s)
A 1 fill in the blank 40
B 2 fill in the blank 41
C 1 fill in the blank 42
D 1 fill in the blank 43
E 1 fill in the blank 44
fill in the blank 45
Develop an activity schedule for the crashed project. If your answer is zero, enter 0.
Earliest Latest Earliest Latest Critical
Activity Start Start Finish Finish Slack Activity
A fill in the blank 46
fill in the blank 47
fill in the blank 48
fill in the blank 49
fill in the blank 50
B fill in the blank 52
fill in the blank 53
fill in the blank 54
fill in the blank 55
fill in the blank 56
C fill in the blank 58
fill in the blank 59
fill in the blank 60
fill in the blank 61
fill in the blank 62
D fill in the blank 64
fill in the blank 65
fill in the blank 66
fill in the blank 67
fill in the blank 68
E fill in the blank 70
fill in the blank 71
fill in the blank 72
fill in the blank 73
fill in the blank 74
F fill in the blank 76
fill in the blank 77
fill in the blank 78
fill in the blank 79
fill in the blank 80
What added project cost is required to meet the six-month completion time?
Total added cost due to crashing $ fill in the blank 82
.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!