Question: PROBLEM 9 A project is depicted by the precedence dias What is the critical path? E 6 A 9 11 F 8 G B 6

PROBLEM 9 A project is depicted by the precedence

PROBLEM 9 A project is depicted by the precedence dias What is the critical path? E 6 A 9 11 F 8 G B 6 13 key ES = earliest start EF = earliest finish D = duration LS = latest start LF - latest finish TF - total float activity description ES DLS EFTF LF (A) A-E-G (B) A-C-F-G (C) B-C-F-G (D) B-D-F-G Hint: The total float of the critical path is always zero