Question: Problem 9. CPM with three time estimates for each activity (5 points) Time (Days) a m 3 1 I I Activity Immediate Predecessor A B

Problem 9. CPM with three time estimates for each activity (5 points) Time (Days) a m 3 1 I I Activity Immediate Predecessor A B C A D A E F C,D,E 1 1 1 2 3 1 2 2 3 b 5 3 3 4 11 5 4 | 4 What is the probability of completing this project in 13 days or more? *Use the critical path to answer this question. (5 points)