Question: Problem 9 Under ABC, Waco, Inc. provided the following information for June of 2015: Estimated Overhead Expected Activity Actual Overhead Actual Activity Setups $18,000 50

Problem 9 Under ABC, Waco, Inc. provided the following information for June of 2015:

Estimated Overhead

Expected Activity

Actual Overhead

Actual Activity

Setups

$18,000

50 setups

$19,400

44 setups

Purchase orders

1,050

525 purchase orders

1,230

522 purchase orders

Product testing

3,500

350 tests

3,150

360 tests

Template etching

1,120

28 etchings

1,100

31 etchings

Facilities

20,000

8,000 sq. feet

21,000

8,000 sq. feet

Totals

$43,670

$45,880

How much will overhead be over or under applied as of the end of June using ABC?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!