Question: Problem 9-07 (Algorithmic) Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is
Problem 9-07 (Algorithmic)
Embassy Club Condominium, located on the west coast of Florida, is undertaking a summer renovation of its main building. The project is scheduled to begin May 1, and a September 1 (17-week) completion date is desired. The condominium manager identified the following renovation activities and their estimated times:
| Immediate | ||
| Activity | Predecessor | Time |
| A | 4 | |
| B | 3 | |
| C | 2 | |
| D | A, B, C | 5 |
| E | A, D | 5 |
| F | C, D | 5 |
| G | D, E | 3 |
| H | F | 2 |
- Which project network is correct?
- What are the critical activities?
- What activity has the most slack time?
- Will the project be completed by September 1? If your answer is zero enter 0. Project Completion Time is _____ weeks. If your answer is zero enter 0.
Earliest Latest Earliest Latest Critical Activity Start Start Finish Finish Slack Activity A Yes or No B Yes or No C Yes or No D Yes or No E Yes or No F Yes or No G Yes or No H Yes or No
Step by Step Solution
There are 3 Steps involved in it