Question: Problem 9-12 (Algorithmic) Assume that the activity time estimates (in days) for the swimming pool construction project are as follows: Activity Optimistic Most Probable Pessimistic
-
Problem 9-12 (Algorithmic)
Assume that the activity time estimates (in days) for the swimming pool construction project are as follows:
Activity Optimistic Most Probable Pessimistic A 5 6 7 B 4 8 15 C 3 4 8 D 2 2 2 E 1 5 9 F 2 5 8 G 2 6 17 H 3 7 8 I 1 8 9 - What are the critical activities? If necessary, round your answers to two decimal places. If your answer is zero, enter 0.
Activity Expected Time Variance A B C D E F G H I
Critical Path:Earliest Latest Earliest Latest Critical Activity Start Start Finish Finish Slack Activity A - Yes
- No
B - Yes
- No
C - Yes
- No
D - Yes
- No
E - Yes
- No
F - Yes
- No
G - Yes
- No
H - Yes
- No
I - Yes
- No
- A-C-F-H-I
- A-D-H-I
- A-D-G-I
- B-C-F-H-I
- B-D-H-I
- B-D-G-I
- B-E-I
- What is the expected time to complete the project? If necessary, round your answer to two decimal places. E(T) = days
- Based only on critical path, what is the estimated probability that the project can be completed in 25 or fewer days? Variance = . If necessary, round your answers to two decimal places. Using the normal distribution, z = . If necessary, round your answers to two decimal places. If negative answer is required, enter the minus sign before the number. Probability of 25 days or less is . If necessary, round your answers to four decimal places. Note: Use Appendix B to identify the probability.
- What are the critical activities? If necessary, round your answers to two decimal places. If your answer is zero, enter 0.