Question: Problem 9-21 (Algorithmic) Consider the following project network and activity times (in days): Activity A B C D E F G Time 6 5 8

Problem 9-21 (Algorithmic)

Consider the following project network and activity times (in days):

Problem 9-21 (Algorithmic) Consider the following

Activity A B C D E F G
Time 6 5 8 8 9 5 5

The crashing data for this project are as follows:

Time (days) Cost ($)
Activity Normal Crash Normal Crash
A 6 5 1000 1300
B 5 4 1600 2300
C 8 6 2200 2600
D 8 6 1600 1900
E 9 8 1800 2050
F 5 4 800 1200
G 5 4 900 1400

Find the critical path and the expected project completion time. If your answer is zero enter 0.

Earliest Latest Earliest Latest Critical
Activity Start Start Finish Finish Slack Activity
A Yes
B No
C Yes
D No
E No
F Yes
G Yes
  1. Critical Path: A-C-F-G Project Completion Time = days
  2. What is the total project cost using the normal times? $
A C E Start Finish B D F G

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!